Work Centers and Routings

Utilizing Odoo manufacturing module, one can produce a product in two different ways. One is via creating a manufacturing order via following simple default stages and complete the production or via customizing the work order by setting up work center and routing mechanisms. To use this advanced manufacturing procedure, one needs enable the routing and planning in the manufacturing settings.
WORK CENTERS

As the name indicates, Work centers are the Physical place situated in one’s business firm, where different manufacturing processes can be done. One can create their work center details with all its performance indices. Later they can use this data to analyze the efficiency and other details of each work center.

Configuration

Manufacturing-Configuration -Settings- Operations-Work Orders

One needs to activate the option work orders. Click SAVE to mark the changes. The change will be reflected in the dashboard as you can see below.

One can manage the work centers directly from dashboard. The user can perform actions and take reports directly from this dashboard.

One can either add the work centers via directly clicking the button WORK CENTERS in the configuration menu or via going to Manufacturing-Master Data-Work Centers

One can create a new work center via clicking the CREATE button.

A creation form includes the following fields: –

Work Center Name: The field defines the name of the work center.
Alternative Work Centers: Alternative Work Centers that can be substituted to this one in order to dispatch production.
Code: The field defines the code for particular work center.
Working hours: Define the schedule of resource. One can either change or modify the working hours via clicking the modify button.

Under General information tab

Capacity: Number of pieces that can be produced in parallel.
OEE Target: Overall Equipment Effectiveness Target in percentage.
Time before prod: Time in minutes for the set up.
Time after prod: Time in minutes for the cleaning.
Cost per hour: Specify the cost of work center per hour.
Analytic accounting: Fill this, only if you want automatic analytic accounting entries on production orders.
Description: Description of the work center.

So, once you start using this work centers, we can analyze what is happening in the work center via clicking any of the buttons shown below.

This helps in knowing on what’s going on and how efficient actually the work center is.
ROUTING

Configuration

Manufacturing-Configuration -Settings- Operations-Work Orders

One can either create a new routing via directly clicking the button ROUTINGS or via going to Manufacturing-Master Data-Routings.

Click CREATE button, to configure new route.

One can provide a name for the routing.
Click “Add a line” to add operations to work centers and time frame.

Under the wizard, you can enter the operation name, select the work center and company.

Here, the duration of the operation can be set in two ways:

– Duration computation: In this method, one can calculate the time duration based on previous work orders.

– Default Duration: in this method, one can enter the duration manually.

Start Next Operation: Set to schedule the next work order after the previous one. By default, there are two types: Once all products are processed and once a minimum number of products is processed.
Description and Worksheet Tab

Under the ‘Description’ tab, one can explain the process involved with each operation. And under the Worksheet, one can upload the process flow as an attachment file.
Linking ‘Route’ to a Manufacturing order.

Linking a created route to a product is done in BoM. Under the Bill of Materials (BoM) one can add the ‘routing’ for a particular product.

Since the manufacturing order is based on the BoM, the system will follow the route specified in, during the manufacturing process. See the figure of a routing enabled manufacturing order.

Check the availability of raw materials via clicking on the “Check availability” button. And click ‘Work orders’, button to create all the work orders according to the routing.

Upon clicking the work order button, one can see the work center specified in the routing.

Click the work order to execute it.

Click ‘PROCESS’ button to start the production.

Click Mark as Done to start a new work order.

#odoodevelopment #odoomanufacturing #odoo13
For More Videos Subscribe to our YouTube channel.

Visit our company website:

Connect with us:
Facebook:
twitter:
LinkedIn:
Pinterest:

#Work #Center #Routing #Odoo #Manufacturing

Similar Posts

4 Comments

  1. avatar
    @johnco001 says:

    Hi there, nice and clear explanation of how to create a routing and production and work orders – however I consider it as incompkete, because you did not proceed with the production order 🙁

  2. avatar
    @kamwenggoh8198 says:

    This video is made much better than many others. Rule #1. You want your audience to get the message.

    This gentlemen spoke clearly, taking time to explain what a field can be used for. A small nit. There is no reason to add background music to it. It does nothing to make the video better. Instead, it just distracts especially when the person is speaking rather softly.

Leave a Reply

Your email address will not be published. Required fields are marked *